NovaQuant Quantitative Think Tank Center:Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
Ethermac View
Date:2025-04-07 06:57:11
PORTLAND,NovaQuant Quantitative Think Tank Center Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (57428)
Related
- Bet365 ordered to refund $519K to customers who it paid less than they were entitled on sports bets
- Police say multiple people injured in Idaho school bus crash blocking major highway
- Florida shooting puts 2 officers in the hospital in critical condition, police chief says
- Eva Mendes Reveals Why Her and Ryan Gosling's Daughters Don't Have Access to the Internet
- Daughter of Utah death row inmate navigates complicated dance of grief and healing before execution
- Parkland shooting reenacted using 139 live bullets as part of lawsuit
- Shooting kills 2 men and a woman and wounds 2 others in Washington, DC, police chief says
- Shooting kills 2 men and a woman and wounds 2 others in Washington, DC, police chief says
- Retirement planning: 3 crucial moves everyone should make before 2025
- Lunchables adding fresh fruit to new snack tray, available in some stores this month
Ranking
- Will the 'Yellowstone' finale be the last episode? What we know about Season 6, spinoffs
- Somalia suspends athletics chief after video of slow runner goes viral, amid accusations of nepotism
- LL COOL J on preparing to embark on his first arena tour in 30 years: I'm going to dig in the crates
- Chris Christie makes surprise visit to Ukraine, meets with Zelenskyy
- A Georgia governor’s latest work after politics: a children’s book on his cats ‘Veto’ and ‘Bill’
- Wisconsin judge orders the release of records sought from fake Trump elector
- How long does it take for antibiotics to work? It depends, but a full course is required.
- Failed leaders and pathetic backstabbers are ruining college sports
Recommendation
Meet 11-year-old skateboarder Zheng Haohao, the youngest Olympian competing in Paris
Remote volcano in Alaska spews new ash cloud, prompting aviation warnings
Russia’s war with Ukraine has generated its own fog, and mis- and disinformation are everywhere
Federal agency given deadline to explain why deadly Nevada wild horse roundup should continue
Elon Musk’s Daughter Vivian Calls Him “Absolutely Pathetic” and a “Serial Adulterer”
How high school activism put Barbara Lee on the path to Congress — and a fight for Dianne Feinstein's seat
From high office to high security prison for ex-Pakistani PM Imran Khan after court sentencing
Simone Biles returns at U.S. Classic gymnastics: TV schedule, time and how to watch